One Stop Service for Artificial Twigs Project
Service: CNC, Die casting, Surface finish ( Powder coating matching the effect of bark) ,Assembly, Testing, Packing and Delivery
Material: Al6061, A380
Quantity: 1 set prototype, 3000 sets die casting parts
Lead time: CNC prototyping: 13 working days
Tooling manufacture: 30 working days
Die casting for 3000 sets: 15 working days
Powder coating: 7 working days
Assembly and packing: 15 working days
About the project
The twigs need to be installed the LEDs and wires inside, they will be assembled into a big artificial tree which will be situated at outside door throughout the year at squares of Norway, Florida and Las Vegas respectively. So the concept of the design must be well fit and waterproof, and the powder coating must be corrosion resistance.